BWI TPC, A JOINT VENTURE - FKC MIDDLE REACH CAPACITY CORRECTION PROJECT PHASE 1
Key Details
Description
FKC MIDDLE REACH CAPACITY CORRECTION PROJECT PHASE 1
Context & Analysis
On Oct 13, 2021, Department of the Interior obligated $187,852,653.69 to BWI TPC, A JOINT VENTURE for fkc middle reach capacity correction project phase 1. The award is classified under NAICS 237990 — OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION. Competition extent: full and open competition with 4 offers received. The procurement used a NO SET ASIDE USED. set-aside. Performance is located in LINDSAY, CA. This award is one of several similar procurements from Department of the Interior under NAICS 237990 — related awards are listed below.
Market context
- Recompete outlook
- Ended Aug 5, 2026 (3 months ago). Recompete signal as of Oct 25, 2026: 20/100, combining time to the end date, the incumbent's history with this agency, whether the award was competed, and its size.
- Competition
- Competed, with 4 offers. 87% of 199 awards in this market (Department of the Interior awards in NAICS 237990 over the last 3 years) were competed; median 3.5 offers.
- Award size
- At $187.9M, this award is larger than 19 in 20 of the 237 priced Department of the Interior awards in NAICS 237990 over the last 3 years (median $1.8M).
- Largest vendors in this market
By obligations, Department of the Interior awards in NAICS 237990 over the last 3 years.
- NW CONSTRUCTION, INC — 10 awards, $1.1B
- KIEWIT INFRASTRUCTURE WEST CO — 3 awards, $538.9M
- GARCO CONSTRUCTION, INC. — 5 awards, $342.7M
- AMES FEDERAL CONTRACTING GROUP LLC — 2 awards, $228.4M
- KREW HEAVY CIVIL LLC — 1 award, $109.0M
Computed from USAspending award data on Oct 25, 2026.
Contractor Information
Similar Awards
THE WORK REQUIRED IS FOR PHASE II OF B.F. SISK DAM SOD MODIFICATIONS.
NW CONSTRUCTION, INC
$257.4M
YOSE 196416 REHABILITATE EL PORTAL WASTEWATER TREATMENT FACILITY AND ADMINISTRATIVE CAMP THE WORK OF THIS CONTRACT IS FOR THE CONSTRUCTION OF: YOSE 196416 REHABILITATE EL PORTAL WASTEWATER TREATMENT FACILITY AND ADMINISTRATIVE CAMP IN YOSEMITE NAT
KIEWIT INFRASTRUCTURE WEST CO.
$217.9M
YOSE 196416 REHABILITATE EL PORTAL WASTEWATER TREATMENT FACILITY AND ADMINISTRATIVE CAMP THE WORK OF THIS CONTRACT IS FOR THE CONSTRUCTION OF: YOSE 196416 REHABILITATE EL PORTAL WASTEWATER TREATMENT FACILITY AND ADMINISTRATIVE CAMP IN YOSEMITE NAT
KIEWIT INFRASTRUCTURE WEST CO.
$217.7M
BF SISK SAFETY OF DAMS (SOD) MODIFICATIONS, PHASE I, THIS PHASE INCLUDES CONSTRUCTION OF SHEAR KEYS, STABILITY BERMS, AND SPILLWAY MODIFICATION. THE PROJECT WILL ADDRESS ISSUES WITH THE SELECT FOUNDATION MATERIALS THAT THE DAM WAS BUILT UPON AND WILL
NW CONSTRUCTION, INC
$139.3M
BF SISK SAFETY OF DAMS (SOD) MODIFICATIONS, PHASE I, THIS PHASE INCLUDES CONSTRUCTION OF SHEAR KEYS, STABILITY BERMS, AND SPILLWAY MODIFICATION. THE PROJECT WILL ADDRESS ISSUES WITH THE SELECT FOUNDATION MATERIALS THAT THE DAM WAS BUILT UPON AND WILL
NW CONSTRUCTION, INC
$136.8M