USCG/CG-SURFACESB$500K to $1M

USCGC HEALY (WAGB-20) Service Life Extension Program Integrated Power Plant system upgrades

Forecast ID: F2026074861

Forecast details

Agency
DHS
Estimated value
$500K to $1M
Set-aside
SB
Contract type
Firm Fixed Price
Vehicle
PO (FAR Subpart 13.5)
Competition
New Requirement, No Contract
Anticipated award
Q3 2027
Estimated solicitation release
March 1, 2027
Requirements contact
(571) 607-7052

Requirement

The Coast Guard is planning to conduct specific sub-system recapitalizations in support of the CGC HEALY Service Life Extension Program (SLEP) from FY2027 to FY 2031. A number of these system recapitalizations require integration and tie-in to the existing Integrated Power Plant (IPP) system. The existing IPP system is comprised of the Central Power Plant (common bus electric propulsion and auxiliary power generation systems) and selected components/systems in the auxiliary machinery plant, which is maintained/managed by a separate services contract. This acquisition is a multi-year contract with the scope focusing on the integration of the recapitalized sub-systems into the IPP system. The sub-systems intended to be recapitalized currently include: the Science Sea Water System Pump and Cyclone Separator, Steering Control System Components, Sanitary System Components, Over-the-Side Weight Handling System, Deaerating Feedwater Tanks, and the Bow Thruster. The IPP system is proprietary and the USCG intends to award to a sole source for this acquisition to the Original Equipment Manufacturer. The Vendor shall provide on-site technical support for training, system testing, commissioning, and certification. The Vendor shall provide maintenance parts lists and a recommended onboard repair parts (OBRP) list for all components.

About this market

Department of Homeland Security awards in NAICS 334511 over the last 3 years.

Typical award size
The median award was $1.1M; the middle half ran from $119K to $7.6M (72 priced awards).
Competition
60% of 84 awards were competed; median 3 offers.
Largest vendors
Largest recent awards
Recompete pipeline
7 contracts of $100K or more in this market end between 90 days and 18 months from now.

Computed from USAspending award data on Oct 25, 2026.

This is a planning forecast, not a solicitation. Dates, values, and set-asides are agency estimates and can change before the official RFP is posted on SAM.gov.