This contract expires in 276 days (Jun 15, 2027).
ERIE AFFILIATES INC - EO 14398 - CONSTRUCTION, BOARDWALK REPLACEMENT @ CUVA
Key Details
Description
EO 14398 - CONSTRUCTION, BOARDWALK REPLACEMENT @ CUVA
Context & Analysis
On Jun 15, 2026, Department of the Interior obligated $1,267,857 to ERIE AFFILIATES INC for eo 14398 - construction, boardwalk replacement @ cuva. The award is classified under NAICS 237990 — OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION. Performance is located in BRECKSVILLE, OH. The contract is scheduled through Jun 15, 2027 — approximately 9 months remaining. This award is one of several similar procurements from Department of the Interior under NAICS 237990 — related awards are listed below.
Contractor Information
Similar Awards
THE WORK REQUIRED IS FOR PHASE II OF B.F. SISK DAM SOD MODIFICATIONS.
NW CONSTRUCTION, INC
$257.4M
YOSE 196416 REHABILITATE EL PORTAL WASTEWATER TREATMENT FACILITY AND ADMINISTRATIVE CAMP THE WORK OF THIS CONTRACT IS FOR THE CONSTRUCTION OF: YOSE 196416 REHABILITATE EL PORTAL WASTEWATER TREATMENT FACILITY AND ADMINISTRATIVE CAMP IN YOSEMITE NAT
KIEWIT INFRASTRUCTURE WEST CO.
$217.9M
YOSE 196416 REHABILITATE EL PORTAL WASTEWATER TREATMENT FACILITY AND ADMINISTRATIVE CAMP THE WORK OF THIS CONTRACT IS FOR THE CONSTRUCTION OF: YOSE 196416 REHABILITATE EL PORTAL WASTEWATER TREATMENT FACILITY AND ADMINISTRATIVE CAMP IN YOSEMITE NAT
KIEWIT INFRASTRUCTURE WEST CO.
$217.7M
FKC MIDDLE REACH CAPACITY CORRECTION PROJECT PHASE 1
BWI TPC, A JOINT VENTURE
$187.9M
BF SISK SAFETY OF DAMS (SOD) MODIFICATIONS, PHASE I, THIS PHASE INCLUDES CONSTRUCTION OF SHEAR KEYS, STABILITY BERMS, AND SPILLWAY MODIFICATION. THE PROJECT WILL ADDRESS ISSUES WITH THE SELECT FOUNDATION MATERIALS THAT THE DAM WAS BUILT UPON AND WILL
NW CONSTRUCTION, INC
$139.3M