This contract expires in 443 days (Aug 26, 2027).
FORGEN LLC - BATTLE CREEK - SOUTH DIVERSION DAM AND CANAL REMOVAL
Key Details
Description
BATTLE CREEK - SOUTH DIVERSION DAM AND CANAL REMOVAL
Context & Analysis
On Feb 23, 2026, Department of the Interior obligated $15,729,975.44 to FORGEN LLC for battle creek - south diversion dam and canal removal. The award is classified under NAICS 237990 — OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION and issued as a firm fixed price contract. Competition extent: full and open competition with 2 offers received. The procurement used a NO SET ASIDE USED. set-aside. Performance is located in PAYNES CREEK, CA. The contract is scheduled through Aug 26, 2027 — approximately 15 months remaining. This award is one of several similar procurements from Department of the Interior under NAICS 237990 — related awards are listed below.
Contractor Information
Similar Awards
YOSE 196416 REHABILITATE EL PORTAL WASTEWATER TREATMENT FACILITY AND ADMINISTRATIVE CAMP THE WORK OF THIS CONTRACT IS FOR THE CONSTRUCTION OF: YOSE 196416 REHABILITATE EL PORTAL WASTEWATER TREATMENT FACILITY AND ADMINISTRATIVE CAMP IN YOSEMITE NAT
KIEWIT INFRASTRUCTURE WEST CO.
$217.7M
BF SISK SAFETY OF DAMS (SOD) MODIFICATIONS, PHASE I, THIS PHASE INCLUDES CONSTRUCTION OF SHEAR KEYS, STABILITY BERMS, AND SPILLWAY MODIFICATION. THE PROJECT WILL ADDRESS ISSUES WITH THE SELECT FOUNDATION MATERIALS THAT THE DAM WAS BUILT UPON AND WILL
NW CONSTRUCTION, INC
$136.8M
BF SISK SAFETY OF DAMS (SOD) MODIFICATIONS, PHASE I, THIS PHASE INCLUDES CONSTRUCTION OF SHEAR KEYS, STABILITY BERMS, AND SPILLWAY MODIFICATION. THE PROJECT WILL ADDRESS ISSUES WITH THE SELECT FOUNDATION MATERIALS THAT THE DAM WAS BUILT UPON AND WILL
NW CONSTRUCTION, INC
$136.8M
THE WORK REQUIRED IS FOR PHASE II OF B.F. SISK DAM SOD MODIFICATIONS.
NW CONSTRUCTION, INC
$134.2M
THE WORK ASSOCIATED WITH THE HYRUM DAM SPILLWAY REPLACEMENT PROJECT WILL TAKE PLACE APPROXIMATELY 9 MILES SOUTHWEST OF LOGAN, UTAH IN CACHE COUNTY, UTAH. THE OVERALL WORK IS FOR THE CONSTRUCTION OF A NEW SPILLWAY AND THE REMOVAL OF THE EXISTING SPILL
AMES FEDERAL CONTRACTING GROUP LLC
$113.3M
Stay Updated
Get notified about new opportunities matching your interests.